The Guadalhorce Hospital has been completed in Cártama on the Costa del Sol, but it has been empty for several months with no opening date planned.To continue installing the equipment in the hospital it has to be accepted as meeting requirement, and to show that hospital is as planned, but for that to take place it must be connected to the electricity supply.The problem is that will cost two million €, although the originally quoted price was 300,000 €, to install the electrical connection required. Endesa say the problem is that to supply the hospital an electrical substation at Villafranca del Guadalhorce will have to be expanded.Cártama Town Hall has said they cannot meet the extra cost, which has put the budget up five fold. Mayor Jorge Gallardo says he thinks the electricity company is...